Consultancy Services for Design and Supervision of 132/33kV Bedyah GS with 2x125MVA and Upgrading of Mudhairib GS to 400kV, Oman

Oman Electricity Company (OETC) floated the Tender for Consultancy Services for Design and Supervision of 132/33kV Bedyah GS and Upgrading of Mudhairib GS to 400kV (later named Construction of 400/132kV Qabel GS). Both Projects, under one Consultancy Contract, were initiated by additional capacity request from regional Electricity Distribution Company (Mazoon Electricity Company) in Al Sharqyia region due to projection of power demand rise in the area. Project was initially divided into two sections: Construction of 132/33kV Bedyah Grid Station and Construction of 400/132kV Qabel Grid Station.

After EPC Contracts awarding, two ENTEL’s supervision teams handled Construction Supervision and Project Management of the projects with following completion dates:

  • Construction of 132/33kV Bedyah GS – Construction completed in December 2018
  • Construction of 400/132kV Qabel GS – Construction completion scheduled for March 2019

Services provided

  • Outline Design
  • Tender Document
  • Flood Risk Assessment
  • Soil Investigation
  • OHL Survey
  • EPC Contract
  • Construction Supervision
  • Project Management

Technical data

  • 1.132/33kV Bedyah GS:
    • 8x 132kV GIS
    • 2x 132/33kV 125MVA Power Transformers
    • 2x 750kVA 33/0.415kV Earthing Auxiliary Transformers
    • CRP, SCS, LVAC, DC System, Telecom System, Firefighting System, etc.
    • Civil Works
  • 1.400/132kV Qabel GS:
    • 10x 400kV GIS and 8x 132kV GIS
    • 2x 400/132kV 500MVA Power Transformers
    • 2x 1000kVA 33/0.415kV Earthing Auxiliary Transformers
    • CRP, SCS, LVAC, DC System, Telecom System, Firefighting System, etc.
    • 1.400/132kV Qabel GS:
    • Civil Works

 

Client

Oman Electricity Transmission Company (OETC)