Lusail Area Development Sewage Treatment Works, Qatar

The project addresses provision of design and consultancy services in relation to the sewage treatment works in Lusail Area Development, including:

  • MBR Sewage Treatment Plant, capacity 60,000 m3/day,
  • Two sewage pump stations, capacity from 450 up to 1950 l/s,
  • One treated effluent pump station capacity 5,000 m3/h
  • 4600 m gravity sewer ranging in size from 800mm diameter to1500mm diameter,
  • 5800 m of raising main range size from 400mm to 800mm diameter,
  • 10 000 m of TSE mains range size from 700mm diameter to 1000mm diameter,
  • 12,100m treated effluent distribution network ranging in size from 200mm diameter to 400mm diameter and SCADA system

Services provided

  • Preliminary Hydraulic Calculation
  • Preliminary Pipeline Route Proposal
  • Preliminary Bill of Quantities
  • Material Size Check Report
  • Preliminary Design Concept Report
  • Route & Invert Level Drawings
  • Standard Detail Drawings for Chambers and Manholes
  • Final Hydraulic Calculation
  • Final Bill of Quantities
  • Surge Analysis Review
  • Design for Fiber Optic Cable
  • Following complete activities related to project execution.

Technical data

  • MBR Sewage Treatment Plant, capacity 60,000 m3/day
  • Two sewage pump stations, capacity from 450 up to 1950 l/s
  • One treated effluent pump station capacity 5,000 m3/h
  • 4600 m gravity sewer ranging in size from 800mm diameter to1500mm diameter
  • 5800 m of raising main range size from 400mm to 800mm diameter
  • 10 000 m of TSE mains range size from 700mm diameter to 1000mm diameter
  • 12,100m treated effluent distribution network ranging in size from 200mm diameter to 400mm diameter and SCADA system.

 

Client

Marubeni Corporation, Japan