| Project Title | Client | Country | Year of Completion |
| WFK Ražanj 2 (86,8 MW) – Preparation of Prefeasibility Study, Preliminary and Design for Building Permit | BAT WIND POWER PLANET DOO | Serbia | Ongoing |
| Solar PV Plant Bela Palanka (150 MW) – Preparation of complete Design Documentation for construction of the Plant, including: Solar PV Plant, SS 400/35kV, BESS, 400kV Switchyard, 400 kV OHL between SS 400/35kV and Switcyard, two 400 kV OHLs for connection of existing 400 kV (between SS Niš 2, Serbia, and SS Sofia, Bulgaria) | AVR SOLAR PARK ISTOK DOO | Serbia | Ongoing |
| Construction of Wind Farm KOSTOLAC (66 MW) – Consultancy Services including: FIDIC Engineer role, Tender preparation, bid evaluation, supervision and design review, Contract management | Electric Power Industry of Serbia – EPS | Serbia | Ongoing |
| Construction of Wind Power Plant ČIBUK 2 (155 MW) – FIDIC Engineer role | ČIBUK 2 WIND ENERGY (Masdar Taaleri Generation company) | Serbia | Ongoing |
| 2 GW Solar PV Plant, Dukhan – Engineering Consultancy Services covering pre-feasibility and full grid compliance / grid impact power system studies for a 2,000 MWp solar PV plant connected to the KAHRAMAA transmission network, including steady-state, dynamic and EMT analyses, power quality and curtailment assessment, utility-grade network modelling and grid code compliance verification | Samsung C&T (QatarEnergy) | Qatar | Ongoing |
| Construction of Al Dur Solar Photovoltaic (SPV) Power Stations – Comprehensive Engineering Consultancy Services for the connection of Al Dur Solar Plant to the 66kV transmission network | Electricity & Water Authority – EWA | Bahrain | Ongoing |
| Strategic Production Portfolio Development of Electric Power Industry of Serbia – Consultancy Services for selection of the best projects for investment | Electric Power Industry of Serbia – EPS | Serbia | Ongoing |
| Construction of New Hydrogen Facilities and Seasonal Thermal Storages within the Electric Power System of Serbia – Feasibility Study | Electric Power Industry of Serbia – EPS | Serbia | Ongoing |
| Integration of New Solar PV (PV3) Plant at Ajban area in Eastern Region of Abu Dhabi (1.5GW) – Consultancy Services for integration of New Solar PV (PV3) Plant including: design review and site supervision during execution and warranty period for PV3 400kV switching station and complete consultancy services for New double circuit 400kV OHL from PV3 to PV2 (90km), LILO of PV3 in existing 400kV OHL TWPS-DHMG (1km) and uprating of existing double circuit 400kV OHL PV2-DHFR (19km) | TAQA Transmission | UAE / Abu Dhabi | Ongoing |
| PV Plant SUNCE TIJOVCA (58MW), SS 110/35kV 2x40MVA, Switchyard 110kV and Connecting to Grid OHL 110kV – Conceptual Design, Preliminary Design, Design for Building Permit | HelloSun doo | Serbia | Ongoing |
| WPP BANAT 1 (93 MW) – Concept Design, Preliminary Design, Design for Building Permit | Vetroelektrana Banat doo Alibunar | Serbia | Ongoing |
| WPP BANAT 2 (145 MW) – Concept Design, Preliminary Design, Design for Building Permit | Vetroelektrana Banat-2 doo Alibunar | Serbia | Ongoing |
| WPP BANAT 3 (93 MW) – Conceptual Design, Basic Design, Design for Building Permit | Vetroelektrana Banat-3 doo Alibunar | Serbia | Ongoing |
| WPP BANATSKO NOVO SELO (125 MW) – Conceptual Design, Preliminary Design, Design for Building Permit | Vetroelektrana Banat-4 doo Beograd | Serbia | Ongoing |
| Transmission Network Development for Clean Energy Transition – Consultancy Services | TAQA Transmission | UAE / Abu Dhabi | Ongoing |
| QatarEnergy Industrial Cities Solar PV Project (875.5 MW) – Grid code compliance and grid impact Power System Studies for two solar PV plants (437.5 MW at Ras Laffan and 438 MW at Mesaieed) – steady-state, dynamic, transient stability, electromagnetic transient (EMT), power quality, protection, arc-flash and RAM studies | Samsung C&T (QatarEnergy) | Qatar | 2025 |
| Construction of Solar PV Plant KLENOVNIK (108.9 MW) – Preliminary Study, Prefeasibility Study and Conceptual Design | Electric Power Industry of Serbia – EPS | Serbia | 2025 |
| Construction of WPP PLANDIŠTE (93.5 MW) – Technical Due Diligence | Electric Power Industry of Serbia – EPS | Serbia | 2024 |
| Construction of Energy-from-Waste (EfW) Plant in Vinča, near Belgrade, with capacity of 340,000 t/year of waste (30 MWel + 56,5 MWth) – Preliminary Design, Design for Building Permit, Detailed Design, Construction Supervision, Permitting services | Beo Čista Energija | Serbia | 2024 |
| Solar PV Plant (600 kW) on the roof and car parking canopies of the Public Parking Utility Company Building in the City of Belgrade – Conceptual Design | Public Parking Utility Company, City of Belgrade | Serbia | 2024 |
| Integration of New Solar PV Plant (at Al Dhafrah Area, Eastern Region of Abu Dhabi), 1.5GW – largest single site PV plant in the world – Consultancy Services including: design review and site supervision during execution and warranty period for PV2 400kV switching station and integration works in LDC of the switching station and Solar PV2 plant | TAQA Transmission | UAE / Abu Dhabi | 2024 |
| Construction of Wind Farm VETROZELENA (300 MW) – Conceptual Design, Preliminary Design, Design for Building Permit and Permitting Services | CWP Global | Serbia | 2023 |
| Construction of Wind Farm BAŠAID (84 MW) – Conceptual Design, Preliminary Design, Design for Building Permit, Permitting Services | Basaid Wind Farm | Serbia | 2023 |
| Construction of Ground Solar PV Plants in the Refinery Complex of the Serbian Petroleum Industry (7,5 MW) | Petroleum Industry of Serbia – NIS | Serbia | 2023 |
| QP Solar Plants (800 MWac) – Preparation of a Model Power Purchase Agreement (PPA) for KAHRAMAA’s procurement of solar energy from 800 MWac PV plants at Ras Laffan and Mesaieed, covering technical, commercial, and legal structuring, including tariff evaluation, deemed energy and curtailment provisions, grid interconnection and operational terms, and stakeholder coordination | Qatar General Electricity & Water Corporation – KAHRAMAA | Qatar | 2023 |
| Roof PV panels installation on the buildings and land owned by Petroleum Industry of Serbia – Techno – economic analysis | Petroleum Industry of Serbia – NIS | Serbia | 2022 |
| Al Kharsaah Independent Solar PV Plant (800 MW) – Consultancy Services for 220/132/33 kV grid connection equipment, including 220/132 kV and 132/33 kV substations, for solar PV plant grid integration – power system studies, concept design, design review, and site supervisionconcept supervision | Power China / Sinohydro (Siraj 1) |
Qatar | 2022 |
| QatarEnergy Industrial Cities Solar PV Project (875.5 MW) – Pre-tender 220 kV grid connection studies for two solar PV plants (437.5 MW at Ras Laffan and 438 MW at Mesaieed) – steady-state, power quality and reactive power capability studies, including equipment verificationstudies, verification | Larsen & Toubro | Qatar | 2022 |
| Roof Solar PV Plant in the Refinery Complex of Petroleum Industry of Serbia (2,4 MW) – Conceptual Design Services | Petroleum Industry of Serbia – NIS | Serbia | 2022 |
| Construction of Wind Farm ALIBUNAR 1 (96,6 MW) and ALIBUNAR 2 (71,4 MW) – Design Services for modification of Building PermitBuilding Permit | WindVision | Serbia | 2021 |
| NEOM Green Hydrogen Project – Power system review and validation studies for the 380 kV transmission system, including steady-state and N-1 contingency studies, thermal capacity assessment, overhead line–to–underground cable transition analysis, and line shunt reactor sizing. | Larsen & Toubro(Neom Green Hydrogen Company and Air Products) | Saudi Arabia | 2021 |
| Al Kharsaah Independent Solar PV Plant (800 MW) – Pre-tender grid connection studies for integration of a new solar PV plant into the KAHRAMAA 132 kV and 220 kV transmission network, covering steady-state, power quality, reactive power compensation, and transformer sizing studies | Larsen & Toubro | Qatar | 2019 |
| Construction of Wind Farm KOVAČICA (104,5 MW) – Design for Execution (roads and foundations) | CJR Renewables | Serbia | 2018 |
| Construction of Wind Farm ČIBUK 1 (160 MW) – Design for Execution for WTG foundation | CJR Renewables | Serbia | 2018 |
| Construction of Wind farm PLANDIŠTE (93.5MW) – Modification of Design for Building Permit | Wind Park Plandište | Serbia | 2018 |
| Construction of Wind Farm BELA ANTA (120 MW) – Consultancy Services related to review and approval of Final Design | Wellbury – Bela Anta | Serbia | 2017 |
| Construction of Wind Farm ČIBUK 1 (160 MW) including connection to the transmission grid – Feasibility Study, Basic Design and Final Design | Vetroelektrane Balkana | Serbia | 2017 |
| Construction of Solar PV Plant on the Roof of the UN House in Belgrade – Consultancy Services related to development of Conceptual Design | United Nations Development Programme – UNDP | Serbia | 2016 |
| Construction of Wind Farm ALIBUNAR 1 (99 MW) – Consultancy Services related to review and approval of Final Design | WindVision Wind Farm A | Serbia | 2016 |
| Construction of Wind Farm ALIBUNAR 2 (75 MW) – Consultancy Services related to review and approval of Final Design | WindVision Wind Farm B | Serbia | 2016 |
| Construction of Solar PV Plant on the Roof of Football Stadion RAJKO MITIC in Belgrade – Business Plan preparation | Donation of Energoprojekt ENTEL | Serbia | 2015 |